This switch must be located no more than 1 meter from the test space and must
be rigidly attached to the machine. Use the included double-sided foam tape to
attach the switch to the machine. Clean surfaces with Isopropyl alcohol before
applying the tape. Sheet-metal screws can also be used.
The ReNew SMA system does not have an e-stop connection, as it does not
interface with the power circuits of the existing load frame.
Important For the safe installation of this product, the existing e-stop on
the load frame must still be functional and accessible.