be certain.mLandmark Test SystemsSite Preparation Guide100-209-144 B
Landmark Test System Site Prep Guide10Facility PreparationGrounding RequirementsEach system has its own internal grounding system, which is common gro
Landmark Test System Site Prep Guide Facility Preparation11AcousticsSome types of fatigue testing can produce noise which is undesirable or potentiall
Landmark Test System Site Prep Guide12Facility PreparationRelative HumidityThe recommended relative humidity for the test room is within the range of
Landmark Test System Site Prep Guide System Component Specifications13System Component SpecificationsContents Load Unit Specifications 14Hydraulic
Landmark Test System Site Prep Guide14Load Unit SpecificationsSystem Component SpecificationsLoad Unit SpecificationsNote Specifications are subject t
Load Unit SpecificationsLandmark Test System Site Prep Guide System Component Specifications15Series 370 Load Frame Specifications Model Base width(A)
Landmark Test System Site Prep Guide16Load Unit SpecificationsSystem Component SpecificationsEnvironmental Requirements—Series 370 Load FramesAll Seri
Hydraulic Power Unit SpecificationsLandmark Test System Site Prep Guide System Component Specifications17Hydraulic Power Unit SpecificationsThe follow
Landmark Test System Site Prep Guide18Hydraulic Power Unit SpecificationsSystem Component SpecificationsModel 505.07/.11 SpecificationsGeneral Specifi
Hydraulic Power Unit SpecificationsLandmark Test System Site Prep Guide System Component Specifications19Model Specific SpecificationsParameter 505.07
Copyright information © 2009-2010 MTS Systems Corporation. All rights reserved.Trademark information MTS is a registered trademark of MTS Systems Corp
Landmark Test System Site Prep Guide20Hydraulic Power Unit SpecificationsSystem Component SpecificationsModel 505.20/.30 SpecificationsGeneral Specifi
Hydraulic Power Unit SpecificationsLandmark Test System Site Prep Guide System Component Specifications21Model Specific SpecificationsParameter 505.20
Landmark Test System Site Prep Guide22Controller SpecificationsSystem Component SpecificationsController SpecificationsEnvironmental Requirements—Seri
Controller SpecificationsLandmark Test System Site Prep Guide System Component Specifications23Specifications–Model 494.04 Chassis All equipment relat
Landmark Test System Site Prep Guide24Controller SpecificationsSystem Component SpecificationsSpecifications–Model 494.06 Chassis All equipment relate
Controller SpecificationsLandmark Test System Site Prep Guide System Component Specifications25Specifications–Model 494.10 ChassisAll equipment relate
Landmark Test System Site Prep Guide26Controller SpecificationsSystem Component SpecificationsSpecifications–Model 494.20 Chassis All equipment relate
Landmark Test System Site Prep Guide Additional Considerations27Additional ConsiderationsContents HPU Considerations 28Load Unit Considerations
Landmark Test System Site Prep Guide28HPU ConsiderationsAdditional ConsiderationsHPU ConsiderationsHPU Cooling Water RequirementsThe hydraulic power u
HPU ConsiderationsLandmark Test System Site Prep Guide Additional Considerations29Softened or distilled water might not be good to use as a cooling li
Landmark Test System Site Prep Guide Contents3ContentsIntroduction 5Facility Preparation 7Preparing to Receive the System 7Space Requirements
Landmark Test System Site Prep Guide30Load Unit ConsiderationsAdditional ConsiderationsLoad Unit ConsiderationsThe load unit is typically shipped in a
Electronic Console ConsiderationsLandmark Test System Site Prep Guide Additional Considerations31Electronic Console ConsiderationsConsole Handling Req
Landmark Test System Site Prep Guide32Computer Console ConsiderationsAdditional ConsiderationsComputer Console ConsiderationsPackaging and movement of
mMTS Systems Corporation14000 Technology DriveEden Prairie, Minnesota 55344-2290 USAToll Free Phone: 800-328-2255 (within the U.S. or Canada)Phone: 95
Landmark Test System Site Prep Guide4ContentsAdditional Considerations 27HPU Considerations 28HPU Cooling Water Requirements 28HPU Electrical
Landmark Test System Site Prep Guide Introduction5IntroductionThe MTS Landmark System is designed to operate in a laboratory or light industry environ
Landmark Test System Site Prep Guide6Introduction
Landmark Test System Site Prep Guide Facility Preparation7Facility PreparationThis section describes the physical, electrical, and mechanical requirem
Landmark Test System Site Prep Guide8Facility PreparationSpace RequirementsConsideration must be given to planning the space requirements around the e
Landmark Test System Site Prep Guide Facility Preparation9The dynamic response characteristics of the foundation should be limited to low levels so th